| I35 Bridge Replacement |
|
Project Location:United States, Minneapolis, Minnesota The Situation:Due to an August 1, 2007 bridge collapse, the I35W highway in Minneapolis, Minnesota needed replacement. The replacement project design incorporated a watertight pedestrian underpass under the new bridge, requiring sealing products of the highest watertight integrity. The Solution:ConSeal products were used to provide this required watertight seal. CS-102 was used to seal the interior section of the joints and CS-212 was used to wrap the exterior of the joints along with CS-75, a water based primer used to ensure a secure seal. Sealant Application:Box Culvert Precaster: Hancock Concrete ConSeal Products Used:CS-75 Water Based Primer CS-102 Butyl Rubber Sealant CS-212 External Joint Wrap Applicable Industry Standards:ASTM C-990 ASTM 877 Type III Case Study Category:Joint Sealants Highway Primers External Joint Wraps |